The Wonderful Company’s growing portfolio of wineries is anchored by one of the most prominent in the Paso Robles region, Justin Vineyards and Winery. In 2024, Precision completed the ground-up construction of Justin’s $22 million,125,000-square-foot insulated-concrete tilt-up wine facility, which includes a 576,000-case robotic racking storage system, 15,000 square feet of luxury offices and amenities spanning two floors, a wastewater treatment system, and bio-retention system. In 2025, Precision built a crush pad, underground auger system, and outdoor wine production area at an adjacent facility.
The building is one of few concrete tilt-ups in the region (most are pre-engineered metal structures). Its 64 concrete panels – each is approximately 50 feet high, 25 feet wide, and 200,000 pounds – are the largest possible panels of this type. Each contains a 7-inch core of polystyrene board insulation; the roof contains two, 3-inch layers of this insulation. The result is a building that is far more energy efficient: Essentially, it is a giant cooler. All panels were lifted into place by an 825-ton crane over a span of just four days, with zero damage or need to patch the surface, which is typical.
Other efficient features include four bio-retention ponds, which collect surface water runoff to replenish the water table, and the facility’s wastewater treatment system, which processes used water for irrigation. The site’s three mature oaks were preserved at grade level and the parking area includes EV charging stations.
Scopes included underground utilities; retaining walls and waterproofing; structural steel package including columns, beams, ledgers, girders, joists, braced frames, and decking; mechanical, electrical, plumbing; structural concrete slab; rigid insulation and membrane roofing; exterior metal stud framing, plaster, metal roofing, storefront glazing; trims and paint; interior office buildout including second-floor metal deck, infilled in concrete and
stairs; metal stud framing, drywall, casework and paint; interior tile, stone countertops and carpet; landscape and irrigation; and finish grading.
Precision provided all project management, site management, quality control, and safety management, and self-performed installation of column protectors, kitchen equipment, bike lockers and racks, fire extinguishers, signage, and pump house roof; crawlspace plywood walkway, material receiving and unloading, water remediation, and general labor.
During the concrete pours in January 2023, Paso Robles experienced record-breaking rainstorms that flooded the site and halted progress. Water pumping and rerouting (filling some of the largest holes in advance of rain, and digging trenches to route water off the site), helped mitigate. The foundation pads were squeegeed after storms (the panels are formed on top of them, and a dry surface is required for a smooth finish). When work could recommence, the project was more than two months behind schedule, and the client urgently needed the finished facility.
Precision reworked the schedule to move up tasks that could be done during wet weather and accelerated the remaining scopes. In the end, Precision regained most of the lost time. And the panel pours were exceptionally successful: No surface required patching or repair, highly unusual even in the best conditions.